At MOEE, Naypyitaw, The Republic of the Union of Myanmar on 28 November 2019,
Senior Colonel Saranyu Viriyavejakul, D.Sc., Vice President of NEDA and others participated in
the meeting to discuss about the progress of the energy projects which Myanmar has asked for
the support from NEDA such as electrical system improvement project (transmission line and
power station) in Myawaddy (66 kV Line project 50 Miles from 230 Myawady Substation to
Sukali (Oakkayeikhta) and 66/11 kV 20 MVA new Substation at Sukali) and electrical system
improvement project in Yangon (North Okkalapa and North Dagon), The Republic of the Union
of Myanmar, with the representatives from Ministry of Electricity and Energy (MOEE) and Yangon
Electricity Supply Corporation (YESC).